Responding to a risk (P6 Professional Only)

If you decide to respond to a risk, you can choose to select a response and to define new risk impacts based on the your response.

Note: The Response section is disabled if you have not selected values in the Pre-Response section for the Probability, Schedule, and Cost fields.

To respond to a risk and develop a response:

  1. If you haven't already done so, do the following to display the Risks details:
    1. Choose Project, Risks.
  2. Display Risk Details.
  3. If not already selected, select the risk for which you want to respond.
  4. Click the Impact tab.
  5. On the Impact tab, Response section:
    1. In the Response Type list, select the appropriate value.
    2. In the Response Description field, type a description of the response.
  6. On the Impact tab, Post-Response section:
    1. In the Probability list, select the appropriate value.
    2. In the Schedule list, select the appropriate value.
    3. In the Cost list, select the appropriate value.
    4. Observe the Score field field. It shows the risk calculation based on the values you selected for the Probability, Cost, and Schedule fields.