Responding to a risk (P6 Professional Only)
If you decide to respond to a risk, you can choose to select a response and to define new risk impacts based on the your response.
Note: The Response section is disabled if you have not selected values in the Pre-Response section for the Probability, Schedule, and Cost fields.
To respond to a risk and develop a response:
- If you haven't already done so, do the following to display the Risks details:
- Choose Project, Risks.
- Display Risk Details.
- If not already selected, select the risk for which you want to respond.
- Click the Impact tab.
- On the Impact tab, Response section:
- In the Response Type list, select the appropriate value.
- In the Response Description field, type a description of the response.
- On the Impact tab, Post-Response section:
- In the Probability list, select the appropriate value.
- In the Schedule list, select the appropriate value.
- In the Cost list, select the appropriate value.
- Observe the Score field field. It shows the risk calculation based on the values you selected for the Probability, Cost, and Schedule fields.