Once a risk has been added, you can assign the risk to an activity to explicitly identify the activity impacted by the risk.
Note: You must have Add/Edit/Delete Risks and Add/Edit Activities Except Relationships privileges to assign or remove risks.
You can assign a risk to an activity while you are adding risks using the Risks view or while managing your activities using the Activities window.
To assign a risk to an activity from the Risks view:
To assign multiple activities, hold down the Ctrl key, then click each activity to assign.
To assign a risk to an activity from the Activities window:
To assign multiple risks, hold down the Ctrl key, then click each risk to assign.