Assign the baseline to use for summarization or earned value

To choose which baseline to use for summarizing a project, open the project for which you want to select a project baseline.

  1. Choose Project, Assign Baselines.
  2. In the Project field, select the project to which you want to assign a project baseline.
  3. In the Project Baseline field, select the desired baseline or the current project. If no baseline is designated as active, the current project is used as the baseline project.

    Note: You can assign only one project baseline to a project. You must have the appropriate security privileges to select the project baseline.