Assign the baselines to use for the current project

Use the Assign Baselines dialog box to choose the primary baseline for a project. Open the projects for which you want to select a baseline.

  1. Choose Project, Assign Baselines.
  2. In the Project field, select the project to which you want to assign a primary baseline.
  3. Select an existing baseline in the Primary field to use an existing baseline as the primary baseline.

    Note:

    If you do not select a value for the primary baseline, the current project is used as the primary baseline.