Assign baselines for comparison

  1. Choose Project, Assign Baselines.
  2. In the Project field, select the project to which you want to assign baselines.
  3. In the Secondary and Tertiary fields, select an existing baseline of the current project.

    Note: The Current Project is automatically used as the Primary baseline; thus, it does not have to be set.