Choose to calculate the earned value from the Budgeted (or Planned) or At Completion values of the project or primary baseline. For example, based on the settings chosen, you can add the budgeted, original, or planned duration to the BL Start date to calculate the BL Finish date, or you can use the duration at completion to calculate the actual baseline finish date.
To choose the type of baseline you want to use to calculate earned value,
To specify how earned value is calculated,
Note: When P6 Professional is connected to P6 EPPM database, preferences for baseline values are set in P6.