Customize collapsed bars in the Gantt Chart

  1. In the Bars dialog box, click Options.
  2. Click the Collapsed Bars tab.
  3. Choose the Collapse to Grouping Bands option to display the activity bars as a single bar.
  4. If the Show Relationships checkbox in the General tab is marked, you can mark the Show Relationships for Collapsed Bars to show relationship lines from the collapsed bar to other collapsed and individual bars.
  5. On the Bars dialog box Bar Settings tab, under the Bar Necking Settings section, mark the Calendar Nonwork Time checkbox to show nonwork time from the activity's calendar as a neck, or thin bar, on the collapsed bar.
  6. Mark the Activity Nonwork Intervals checkbox to show a neck, or thin bar, for activity and/or calendar nonwork time, including suspend/resume dates.