Add a curtain attachment in a Gantt Chart

  1. In the Activities window, click the Layout Options bar and choose Attachments, Curtain, Add Curtain.
  2. Mark the 'Display curtain attachment' checkbox.
  3. Click to select the Start and Finish Dates.
  4. Select the color to use for the curtain.
  5. Select the fill pattern for the curtain date range.
  6. Click OK.

Tip

Notes