Assign a calendar to an activity

  1. Choose Project, Activities.
  2. Select the activity whose calendar you want to define.
  3. Display Activity Details, then click the General tab.
  4. In the Activity Calendar field, click .
  5. Choose the calendar that you want to assign to the selected activity, then click the Select button.

Tip

Related Topics

Display window details



Legal Notices
Copyright © 1999, 2016, Oracle and/or its affiliates. All rights reserved.

Last Published Wednesday, May 25, 2016