Assign a curve to a resource or role assignment

You can assign a resource distribution curve to any resource or role assignment on activities with a duration type of Fixed Duration and Units/Time or Fixed Duration & Units. Resource usage and costs are distributed evenly during an activity unless you specify nonlinear distribution using curves.

  1. Choose Project, Resource Assignments.
  2. Select the resource/role assignment to which you want to assign a resource curve.
  3. Double-click in the Curve column and select the curve you want to assign to the resource/role assignment, then click Select.

    To display the Curve column, click the Display Options bar, then choose Columns, Customize. Select Curve from the General group and click to add the column to the Selected Options.

Tips

Notes

Related Topics

Manually enter future period assignment values

Future period bucket planning