Assign WBS weighted milestones

  1. Choose Project, WBS.
  2. Select the WBS element to which you want to assign weighted milestones, then click the Earned Value tab.
  3. In the Technique for Computing Performance Percent Complete area, choose WBS Milestones Percent Complete.
  4. Click the WBS Milestones tab.
  5. Click Add, then type a name of the task or portion of work signifying a milestone for the selected WBS element in the WBS Milestone column.
  6. Click the corresponding field in the Weight column, then type a number indicating the significance of this milestone relative to the others listed.
  7. Mark the checkbox in the Completed column when each milestone is complete.
    The WBS element's percent complete is calculated based on the weight of the completed milestone in relation to the remaining milestones.

Note

Applying this formula to the previous example, the completed milestone has a weight of 9.0, and is divided by the total weight of all milestones (12.0), to equal 75% complete.