Change a Gantt Chart bar's settings

  1. Choose View, Bars.

    You can also click the Layout Options bar and choose Bars.
  2. Select the Gantt Chart bar for which you want to change the label.
  3. Click the Bar Settings tab.
  4. To include the selected bar when you collapse the display to summary-level information, select Show bar when collapsed.
  5. To display the selected bar as a summary bar only, select Show bar for grouping bands.
  6. To show the selected bar's nonwork time as a neck based on the activity's calendar, select Calendar nonwork time.
  7. To show the selected bar's nonwork intervals as a neck based on out-of-sequence progress and suspended/resumed activities, select Activity nonwork intervals.
  8. Click OK.

    To view your changes without closing this dialog box, click Apply.