Change a Gantt Chart bar's timescale

  1. Display the Gantt Chart, then choose View, Top Layout Options, Bars.
  2. Select the bar.
  3. In the Timescale column, select the timeperiod you want the bar to represent.
  4. To preview the new bar without closing the Bars dialog box, click Apply.

Here is more detail about specifying a bar's timescale:

Depending on whether an activity layout or a tracking layout is displayed, the options vary for specifying the timeperiod represented by a Gantt Chart bar. Some timeperiods are available for both layout types. In activity layouts the bars represent dates for an activity; in tracking layouts, depending on the current view, bars may represent an EPS node, project, or WBS element.

To represent this value:

Select this bar:

Start Date to Finish Date

Current Bar

Percent Complete

% Complete Bar

Performance Percent Complete

Performance % Complete Bar

Planned Start Date to Planned Finish Date

Plan Bar

Actual Start Date to Actual Finish Date

Actual Bar

Remaining Start Date to Remaining Finish Date

Remain Bar

Primary Baseline Planned Start Date to Primary Baseline Planned Finish Date

Primary Baseline Bar

Secondary Baseline Planned Start Date to Secondary Baseline Planned Finish Date

Secondary Baseline Bar

Tertiary Baseline Planned Start Date to Tertiary Baseline Planned Finish Date

Tertiary Baseline Bar

Early Start Date to Early Finish Date

Early Bar

Late Start Date to Late Finish Date

Late Bar

Remaining Finish Date to Late Finish Date

Float Bar

Remaining Finish Date to Late Finish Date with Remaining after the late date

Neg Float Bar

User start and end dates defined in the activity columns

User Defined Bars

Related Topics

Change a layout's timescale format