Change an activity's start and finish dates in the Gantt Chart

  1. Move the mouse pointer over the activity’s Gantt Chart bar end until it displays a hand pointer.
  2. Click and hold the mouse button.

    To move the activity’s start date and finish date back in time, drag the bar to the left.

    To move the activity’s start date and finish date forward in time, drag the bar to the right.