Change data globally

  1. Choose Tools, Global Change.
  2. Click New.
  3. Select a Subject Area.
  4. Type a name to identify the global change specification.
  5. Define If, Then, Else and statements to specify the data you want to change.

    Click Add to define additional If, Then, or Else statements.
  6. Click Change.
  7. To accept the changes, click Commit Changes; to cancel the global change and return the data to its original state, click Cancel Changes.

Notes

When connected to a P6 EPPM database: If you are applying a global change to a unit or duration field, the Use the assigned calendar to specify the number of work hours for each time period checkbox (set using the P6, Application Settings) is ignored if set. Because it is ignored, the global change applies the unit or duration value based on the Application Settings hours per time period settings.



Legal Notices