Change the project leveling priority

  1. Choose Enterprise, Projects and display Project Details.
  2. Click the General tab, then select a leveling priority from 1 (highest priority) to 100 (lowest priority).

    During leveling, this number determines which assignments from other projects to consider within the leveling run. For example, if you specify 5 in the Consider Assignments in Other Projects With Priority Equal/Higher Than field of the Level Resources dialog box, all projects with a project leveling priority of 1, 2, 3, 4, and 5 are considered.

Note

Tips

Related Topics

Display window details



Legal Notices
Copyright © 1999, 2016, Oracle and/or its affiliates. All rights reserved.

Last Published Wednesday, May 25, 2016