Choose the rate source for an assignment

When a resource and role share an assignment on the same activity (e.g., when you assign a resource that has an assigned role to an activity), you can choose to use the rate of the resource or role to calculate costs, or enter a custom rate.

  1. Choose Project, Activities.
  2. Select the activity that contains the assignment.
  3. Display Activity Details, then click the Resources tab.
  4. In the Resources tab, double-click the Rate Source column and choose Resource, Role, or Override.

    Choose Resource to calculate cost based on the resource's price/unit value selected in the Rate Type column. Choose Role to calculate cost based on the role's price/unit value selected in the Rate Type column. Choose Override if you want to enter a custom rate in the Price/Unit column.