Copy and paste activities in the Activity Network

  1. Select the activity you want to copy. To select multiple activities, use Ctrl+click.
  2. Click Edit, Copy.
  3. Select the group band or another activity within the group band where you want to insert the copied activities, then click Edit, Paste.

    If activities are not grouped in the Activity Network, you do not need to select a group band.
  4. In the Copy Activity Options dialog box, mark the checkbox next to each type of information you want to copy, then click OK.
  5. In the Renumber Activity IDs dialog box, select how to create activity IDs for copied activities. Click OK.

    If you selected the Replace Beginning Characters option on the previous dialog box, the Duplicates dialog box may appear after clicking OK. If it appears, enter a new activity ID and click OK.

Note:

When connected to a P6 EPPM database: When you copy and paste activities within the same project, any associated risks from P6 are also copied; risks are not copied when you copy and paste activities to a different project.

When connected to a P6 Professional database: When you copy and paste activities within the same project, any associated risks are also copied; risks are not copied when you copy and paste activities to a different project.



Legal Notices
Copyright © 1999, 2016, Oracle and/or its affiliates. All rights reserved.

Last Published Wednesday, May 25, 2016