Copy and paste activities in the Activity Table

  1. Select the activity you want to copy. To select multiple activities, use Ctrl+click.
  2. Click Edit, Copy.
  3. Select the WBS band where you want to insert the copied activities, then click Edit, Paste.
  4. In the Copy Activity Options dialog box, mark the checkbox next to each type of information you want to copy, then click OK.
  5. In the Renumber Activity IDs dialog box, select how to create activity IDs for copied activities. Click OK.

    If you selected the Replace Beginning Characters option on the previous dialog box, the Duplicates dialog box may appear after clicking OK. If it appears, enter a new activity ID and click OK.

Note:

When connected to a P6 EPPM database: When you copy and paste activities within the same project, any associated risks from P6 are also copied; risks are not copied when you copy and paste activities to a different project.

When connected to a P6 Professional database: When you copy and paste activities within the same project, any associated risks are also copied; risks are not copied when you copy and paste activities to a different project.