Define price/unit rates for roles

You can add up to five price per unit rates for each role in the roles dictionary. When you assign a role to an activity during project planning, you can choose which rate you want to use to calculate cost. Defining rates for specific roles yields more accurate project cost planning results.

  1. Choose Enterprise, Roles.
  2. Select the role you want to assign rates to, then click the Prices tab. If tabs are not displayed in the Roles dialog box, click the Display Options bar and choose Roles Details.
  3. Enter up to five Price/Unit rates for the selected role.

    For example, if the price per unit is $25 per hour, enter 25h; if the price per unit is $50000 per year, enter 50000y. You can only enter unit values in minutes, hours, days, weeks, months, and years. Your system administrator defines the abbreviations for these units in the Admin Preferences, Time Periods tab when P6 Professional is connected to a P6 Professional database in P6, Application Settings when connected to a P6 EPPM database.

Notes