Enter activity durations

  1. Choose Project, Activities.
  2. Select the activity whose duration you want to enter.
  3. Display Activity Details, then click the Status tab.

    To enter original or planned duration for the activity, in the original or planned field, type the amount of time followed by the time period.

    To enter the actual duration for the activity, in the Actual field, type the amount of time followed by the time period. You can only enter actual duration for activities that are completed.

    To enter the remaining duration for the activity, in the Remaining field, type the amount of time followed by the time period. You can only enter remaining duration for activities that are in progress.

    To enter at completion duration for the activity, in the At Complete field, type the amount of time followed by the time period. You can only enter at completion duration for activities that are not started or in progress.