Enter cost information for resource assignments

  1. Choose Project, Activities.
  2. Select the activity whose costs you want to enter.
  3. Display Activity Details, then click the Resources tab.
  4. To enter the budgeted or planned cost for the activity, type the value in the Budgeted or Planned Cost column.

    To enter the actual cost for the activity, type the value in the Actual Cost column.

    To enter the remaining cost for the activity, type the value in the Remaining Cost column. You can only enter remaining cost for activities that are in progress.