Import Contract Management data
Once you link P6 Professional to Contract Management and link your project to a Contract Management project, you can specify which schedule, cost, and dictionary information to import. See Link P6 Professional to Contract Management. See Link your project to a Contract Management project .
- Choose File, Import from Contract Management.
This option is enabled when the project is linked to a Contract Management project on the Contract Management tab of Project Details.
- Mark the checkbox next to each item that you want to import to your project.
- Click Import, then click OK.
- The Contract Management Import Report lists all the information that is imported to your project. Click Commit Changes, then click Yes or No to save the report to a log file. If you select Yes, specify a filename and location.
- Click Close. Click Yes to save any changes you made to the import settings or No to discard changes.
How data is imported from Contract Management