Import projects in XER format

  1. Choose File, Import.
  2. Choose Primavera PM (XER). Click Next.
  3. Choose Project.
  4. Select the file you want to import.
  5. Double click the Import Action field to select how the project data is imported, then specify where to import the projects in the Import To field.

    Select Update Existing Project to add any new/modified data in the XER file to an existing project.

    Selected Create New Project to create a new project while the existing project's data remains the same.

    Select Replace Existing Project to delete the existing project and replace is will the project imported from the XER file.
  6. Choose the data to import by modifying the layout configuration in the Update Project Options dialog box (if necessary).

    In the Modify Import Configuration dialog box, select the data you want to modify. If resource security is enabled, some restrictions apply when importing activity resource assignments.

    Select the action to perform during the import process. Mark the Delete checkbox to remove unreferenced data (i.e., data in the project you are updating but is not included in the import file) from the project. (The Delete field applies only to relationships to external projects, thresholds, activities, activity relationships, and activity resource assignments. Global data types are not affected by this setting.)
  7. Select the currency in which to import cost fields. (This dialog box only displays if the import file does not specify a currency, or if the currency does not match a currency defined in P6 Professional when P6 Professional is connected to a P6 Professional database and using P6 when connected to a P6 EPPM database.)
  8. Click Finish.
  9. Click Close.

Notes



Legal Notices
Copyright © 1999, 2016, Oracle and/or its affiliates. All rights reserved.

Last Published Wednesday, May 25, 2016