Modify check in update options

  1. Open the projects you want to check in.
  2. Choose File, Check In, then select the project you want to check in.
  3. In the Update Project Options dialog box, select the layout you want to modify and click Modify.
  4. In the Modify Import Configuration dialog box, select the data you want to modify.
  5. Select the action to perform during the check-in process.
  6. Mark the Delete checkbox to remove unreferenced data, data in the project you are updating but not included in the check-out file, from the project.
  7. Click OK.