Remove a curve from a resource or role assignment

  1. Choose Project, Resource Assignments.
  2. Select the resource/role assignment from which you want to remove the resource curve.
  3. Click in the Curve column, then click Clear in the Select Curve dialog box.

    To display the Curve column, click the Display Options bar, then choose Columns, Customize. Select Curve from the General group and click to add the column to the Selected Options.

Note



Legal Notices