Schedule a project automatically

Follow these steps to turn on "automatic scheduling" so that the schedule calculates each time you add or delete an activity or relationship, change an activity duration or relationship type, or change anything that affects schedule dates.

  1. Choose Tools, Schedule.
  2. Click Options.
  3. In the General tab, mark the Schedule Automatically When a Change Affects Dates checkbox.
  4. If you want to level resources automatically after it schedules, mark the Level Resources During Scheduling checkbox.
  5. Click Close, then click Schedule.