Sort activities

You can specify one or more sorting criteria to control the order of activities in a layout.

  1. Choose Project, Activities, then choose View, Group and Sort By, Customize.
  2. Click Sort.
  3. Click Add.
  4. Click the Field Name column to select the field by which you want to sort.
  5. Double-click the Sort Order column, then select a sort order: ascending (alphabetically from lowest to highest), descending (alphabetically from highest to lowest), or hierarchical (option only appears for fields that are hierarchical).

    To sort by additional fields, repeat steps 3 through 5.
  6. Click OK.
  7. To preview your changes, click Apply.