Suspend or resume an activity's progress

At some point in the project, you may need to stop work on an activity for a period of time. Indicate this interruption by specifying suspend and resume dates in the Status tab of Activity Details.

  1. Display Activity Details.
  2. Click the Status tab.
  3. In the Activities window, select the activity you want to suspend.
  4. In the Status tab, enter a Suspend date.

    When the activity resumes, enter a Resume date.

Tips

Notes

Related Topics

Display window details



Legal Notices
Copyright © 1999, 2016, Oracle and/or its affiliates. All rights reserved.

Last Published Wednesday, May 25, 2016