Synchronizing activity duration, units, and resource units/time

P6 Professional automatically synchronizes the duration, labor/ nonlabor units, and resource units/time for activities so that the following equation is always true for each activity:

Duration = Units ¸ (Resource Units ¸ Time)

However, since three variables are involved (duration, units, and resource units/time), when you change the value of one variable, P6 Professional must alter the value of a second to balance the equation. The Duration Type setting for an activity allows you to control how P6 Professional synchronizes these variables when any one of the equation's variables is changed.

The following table lists the value that is automatically changed by P6 Professional to synchronize the variables whenever the value of one of the duration type variables is changed.

Activity duration type

When you change units, this value changes...

When you change duration, this value changes...

When you change units/time, this value changes...

When you add a resource and there are no budgeted or planned units, this value changes...

When you add additional resources, this value changes...

Fixed units/time

Duration

Units

Duration

Units

Duration

Fixed Duration & units/time

Units/Time

Units

Units

Units

Units

Fixed units

Duration

Units/Time

Duration

Units

Duration

Fixed Duration & units

Units/Time

Units/Time

Units

Units

Units/Time of each resource