Update a baseline

As a project progresses, you may want to update baseline data without restoring the baseline or creating a new baseline. When a project is in progress, creating a new baseline may not yield accurate comparison results. When you update a baseline, only the data types you select will be updated.

Note: Unless you are working on a standalone system connecting to an SQLite database, you must use JRE 7 or higher to update baselines.

  1. Choose Project, Maintain Baselines.
  2. In the Maintain Baselines dialog box, select the baseline you want to update.
  3. Click Update.
  4. In the Update Baseline dialog box, select the types of data you want to update.

    For project-level data, you can choose to update project details, work products and documents, and risks, issues, and thresholds. You do not have to select any of these options.

    Note: If you choose to update project details, the following items are NOT updated: all data in the Default, Settings, and Resources tabs; the Risk Level and the Project Leveling Priority fields in the General tab; and, the Default Price/Unit for Activities Without Resource or Role Price/Units field in the Calculations tab.

    For activity-level data, you can choose to update all activities or activities that meet a filter's criteria. If you choose to update activities based on a filter, click the browse button to select a filter. If you choose to update all activities, the module overwrites all activities in the baseline.

    You can also choose to add new activities to the baseline, delete activities from the baseline that are no longer in the project, and update existing activities with new activity data. If you only want to update project-level data (and not activity-level data), clear all of the activity-level data options.

  5. If you are updating existing activity data, click Update Options.
  6. In the Update Baseline Options dialog box, select the types of activity and resource/role assignment data you want to update.

    Note: If you choose to update 'Dates, durations, and data date' in the Update Baseline Options dialog box, the following date fields are NOT updated because they are calculated by the scheduler: Early Start, Early Finish, Late Start, and Late Finish. To ensure that these fields are updated, after you run the baseline update, you should restore the baseline project, then schedule and re-baseline the project.

  7. Click OK.
  8. In the Update Baseline dialog box, you can enter or select a filename to log errors during the update process (when connected to a P6 Professional database only).
  9. Click Update.

Tips

Notes

When connected to a P6 EPPM database: You must have the appropriate global and project privileges as defined in P6 to update a baseline.



Legal Notices
Copyright © 1999, 2016, Oracle and/or its affiliates. All rights reserved.

Last Published Wednesday, May 25, 2016