Update progress for individual activities

  1. Choose Project, Activities, then select the activity you want to update.
  2. Display Activity Details, then click the Status tab.

    To update actual dates, mark the Started checkbox, then specify the actual start date in the Started field. If the activity is complete, mark the Finished checkbox, then specify the actual finish date in the Finished field.

    -Or-

    To update activities with Duration percent complete type, click the Remaining field and type the remaining number of workperiods needed to complete the selected activity. When you schedule or apply actuals, the actual duration is calculated as the total working time from the actual start date to the current data date (for in-progress activities) or to the actual finish date (for completed activities), using the activity’s calendar.

    -Or-

    To update activities with Physical percent complete type, type the physical percent complete and the remaining duration for the activity. If resources are assigned, you must also update each resource’s actual regular units.
  3. Repeat the previous steps for each activity you want to update.

Tips