Update progress for spotlighted activities

Use the Progress Spotlight feature (View, Progress Spotlight) to highlight activities in the layout that have started, progressed, or finished between the previous data date and the new data date. If you have the project privileges required to schedule projects, level resources, and apply actuals, you can status the activities that have been highlighted. To update the progress of these activities:

  1. Choose Tools, Update Progress.
  2. If you do not want to use the current data date to update progress, select a new data date.
  3. Choose to update all highlighted activities in the Gantt Chart, or to update the activities that have been selected.
  4. When actuals are applied from timesheets, choose to recalculate the remaining duration based on the activity duration type or to always recalculate it. If you choose to always recalculate, all activities are treated as Fixed Units and Fixed Units/Time.
  5. Click Apply.