Use the Activities tab to assign activities to a risk or to delete activity risk assignments.
Project: The Project ID of the activity assignment.
Activity ID: The Activity ID of the activity assignment.
Activity Name: The Activity Name of the activity assignment.
Start: The current start date of the activity.
Finish: The current finish date of the activity.
Assign: Click to assign activities to the selected risk.
Remove: Click to remove activities from the selected risk.