Change an activity's cost breakdown structure assignment (P6 EPPM Only)

  1. Choose Projects, Activities.
  2. Select the activity whose CBS assignment you want to define or change.
  3. In the Activity Table, double-click in the CBS column, then click .
  4. Select the CBS code to which you want to assign the selected activity. CBS codes are created in Primavera Unifier for the linked project's cost sheet.
  5. Click the Select button.