Assign baselines to projects
You can assign a project baseline to use for summarization purposes and up to three baselines to use for comparison purposes.
- Choose Project, Assign Baselines.
- In the Project field, select the project to which you want to assign baselines.
- To set an existing baseline as the project, primary, secondary, or tertiary baseline, select a baseline from the menu in the appropriate field.
To use the current state of the project as the project, primary, secondary, or tertiary baseline, select the current project from the menu in the appropriate field.
Notes
- You can only assign one project, primary, secondary, and tertiary baseline to a project.
- Secondary and tertiary baselines are not required.
- When connected to a P6 Professional database: You must have the Edit Project Details Except Costs/Financials project privilege to set the project baseline.
When connected to a P6 EPPM database: You must have the appropriate project privilege as defined in P6 to set the project baseline.