- Choose Enterprise, Projects, then select the project whose data date you want to change.
If a single project is open, you can change the data date directly on the Schedule dialog box
(choose Tools, Schedule).
- Display Project Details, then click the Dates tab.
- In the Data Date field, type the new data date or click
to select a date.