Estimate to Complete (ETC)

Estimate to Complete

The estimated cost to complete the activity. Computed as either the remaining total cost for the activity (Remaining Total Cost), or as PF * (Budget at Completion - Earned Value Cost), depending on the earned-value technique selected for the activity's WBS.