A Start Date Variance threshold value is a specified number of days. An issue is generated if the difference between the activity's baseline and current start dates (calculated as BL Start - Start Date) falls beyond the threshold values.
A negative value for Start Date Variance indicates that the current start date is later than the primary baseline start date.