Use the Tools toolbar to schedule and summarize projects, level resources, update progress, apply actuals, store period performance, and much more. This toolbar is displayed by default.
The following table provides information about each available icon on the toolbar.
Icon | Function | Displays by default? | Enabled when active window is: | Shortcut keys | Corresponding menu command |
---|---|---|---|---|---|
| Opens the Primavera P6 Visualizer. See Launching P6 Visualizer from P6 Professional for more information. | Yes | Activities | None | Tools > Visualizer |
| Opens the Schedule dialog box. In this dialog box, you can schedule the open projects and set scheduling options. | Yes | All | F9 | Tools > Schedule |
| Opens the Level Resources dialog box. In this dialog box, you can level resources and set resource leveling options. | Yes | All | Shift+F9 | Tools > Level Resources |
| Enables or disables the Progress Spotlight feature. When Progress Spotlight is enabled, the module highlights the activities that fall between the last data date and the new data date in the Gantt Chart. | Yes | Activities | None | View > Progress Spotlight |
| Shows or hides the progress line in a Gantt Chart. The progress line shows the progress of activities and how the project is performing relative to the baseline project. | Yes | Activities | None | Tools > Progress Line |
| Opens the Update Progress dialog box. In this dialog box, you can estimate progress for spotlighted or selected activities. | Yes | Activities | None | Tools > Update Progress |
| Opens the Global Change dialog box. In this dialog box, you can make changes to all activities, resource assignments, or project expenses, or a selected group of these items, at one time. | No | All | None | Tools > Global Change |
| Opens the Apply Actuals dialog box. In this dialog box, you can update the schedule by applying actuals up to the data date you select for each open project. | No | All | None | Tools > Apply Actuals |
| Enables or disables automatic reorganization. By default, automatic reorganization is enabled. When you turn on Disable Auto-Reorganization, the module does not automatically reorder the currently active window according to your recent changes. | No | All | Shift+F2 | Tools > Disable Auto-Reorganization |
| When connected to a P6 Professional database: Enables you to summarize open projects, or summary-only projects, or all projects. When connected to a P6 EPPM database: Enables you to summarize open projects, or all projects.
To choose which projects you want to summarize, click | No | All | None | Tools > Summarize |
| Enables you to summarize all projects. | No | All | None | Tools > Summarize > All Projects |
| Enables you to summarize open projects. | No | All | None | Tools > Summarize > Open Projects |
| This icon appears only when P6 Professional is connected to a P6 Professional database. Opens the Job Services dialog box. In this dialog box, you can create jobs and schedule them to run automatically on any number of projects or EPS nodes at a specified time. | No | All | None | Tools > Job Services |
| Opens the Store Period Performance dialog box. In this dialog box, you can store past period actuals for any open project in defined financial periods. | No | All | None | Tools > Store Period Performance |
| Opens the Monitor Thresholds dialog box. In this dialog box, you can monitor all of the open project's thresholds at once. | No | All | None | Tools > Monitor Thresholds |
| Opens the Recalculate Assignment Costs dialog box. In this dialog box, you can recalculate resource and role assignment costs for all activities in the open projects. | No | All | None | Tools > Recalculate Assignment Costs |
| Opens the Issue Navigator dialog box. In this dialog box, you can track the open project's issues, including associated activities, resources, and work breakdown structure (WBS) elements. | No | All | None | Tools > Issue Navigator |
| This icon appears only when P6 Professional is connected to a P6 Professional database. Opens the Job Status dialog box. In this dialog box, you can view the status of all jobs submitted in P6 EPPM, such as apply actuals or summarize jobs that were run from P6 Professional and sent to run as an ASAP service. | No | All | None | Tools > Job Status |
Highlight activities for updating
Graph tab - Resource Usage/Role Profile Options dialog box
Graph tab - Resource Usage/Role Profile Options dialog box - for stacked histogram
Apply a Progress Line to the Gantt Chart
Reorganizing window data automatically
Automating processes with Job Services (P6 Professional Only)
Recalculate resource and role assignment costs