Assign a rate type to a resource assignment

You can choose the price/unit rate you want to use to calculate costs for a resource or role assignment on an activity.

  1. Choose Project, Activities.
  2. Select the activity that contains the assignment to which you want to assign a rate type.
  3. Display Activity Details, then click the Resources tab.
  4. Click in the Rate Type column and select the rate type you want to use for the assignment.

    The rate type determines the price/unit used to calculate costs for the assignment. The names for each rate type are defined by your system administrator in the Rate Types tab of Admin Preferences when P6 Professional is connected to a P6 Professional database and in P6 when connected to a P6 EPPM database. When you select a rate type, the monetary value is updated automatically in the Price/Unit column (if displayed).

Tip

Notes

Related Topics

Choose the rate source for an assignment

Display window details



Legal Notices
Copyright © 1999, 2016, Oracle and/or its affiliates. All rights reserved.

Last Published Wednesday, May 25, 2016