Create a baseline

  1. Open the projects for which you want to create a baseline.
  2. Choose Project, Maintain Baselines, then, if more than one project is open, select the projects for which you want to create a baseline.

    If you want to copy the current project as a new baseline, you can select multiple projects; a baseline will be created for all selected projects. If you want to convert another project to a baseline, you can select only one project.
  3. Click Add.
  4. Choose to save a copy of the current project as a new baseline or convert another project into a baseline of the current project, then click OK.

    If you choose to convert another project, select the project in the Select Project dialog box, then click the Select button.

Tip

Notes

Related Topics

Update a baseline

Modify a baseline manually