BlogRead the Latest Articles

How to Print the Activity Code Dictionary From Primavera P6

In Primavera P6 Professional, go to Tools, Reports, Reports and in the Administration & Security report group, run "CV-03 Activity Code Values" if it is available.
If that report is not available, you can create one with the following steps:

1. Go to Tools, Report Wizard.
2. Select Activity Codes subject area. Then from "Additional subject areas", Activity Code Values.
3. At the 'Configure Selected Subject Areas" step, select Activity Codes, Group and Sort then check "Hide if empty" and OK.
4. Continue with the Wizard until you can save the report. Then run it.


Webinar:Schedule Integration with Oracle Primavera Cloud

24th of November 2020

Project schedulers would appreciate the difficulty of integrating different contractor schedules and build a master program out of them.


Oracle Primavera Cloud may lend a helping hand and save many days of work. With cloud and collaborative features, enforcing standard data structures and advanced scheduling capabilities, it can streamline the schedule building and review process. 

Join us to see how!
This free webinar will be delivered in English.

Click here to register!

 

Giriş yapmak için size sağlanan kullanıcı adını ve şifrenizi giriniz