How Primavera P6 calculates "Summary Schedule Percent Complete"

The Schedule % Complete specifies how much of the activity's baseline duration has been completed so far. Computed based on where the current data date falls between the activity's baseline start and finish dates. 

The Schedule Percent Complete is used to compute planned value.  Schedule Percent Complete, when displayed on an organized band and at the Project level, will ALWAYS be calculated as:

(BCWS * 100) / BAC

where

BCWS = Budgeted Cost Work Scheduled or Planned Value Cost
BAC  = Budget At Completion

regardless of what earned value technique is selected for the activity's WBS.

Webinar:Schedule Integration with Oracle Primavera Cloud

24th of November 2020

Project schedulers would appreciate the difficulty of integrating different contractor schedules and build a master program out of them.


Oracle Primavera Cloud may lend a helping hand and save many days of work. With cloud and collaborative features, enforcing standard data structures and advanced scheduling capabilities, it can streamline the schedule building and review process. 

Join us to see how!
This free webinar will be delivered in English.

Click here to register!

 

Giriş yapmak için size sağlanan kullanıcı adını ve şifrenizi giriniz