The Schedule Percent Complete is used to compute planned value. Schedule Percent Complete, when displayed on an organized band and at the Project level, will ALWAYS be calculated as:
(BCWS * 100) / BAC
where
BCWS = Budgeted Cost Work Scheduled or Planned Value Cost
BAC = Budget At Completion
regardless of what earned value technique is selected for the activity's WBS.